10th May 2012
On site meeting with ERDF (company for the distribution of electricity networks) for the connection of the provisional electrical supply.








8th May 2012
Awaiting updated quotes from Véolia eau ( distribute and manage water and sewer systems) to achieve independant villa water supply. Awaiting return call President of Domaine des Dolmens for information on land use below villa (espace vert) . Awaiting propositions re type of pool cover available for present design


7th May 2012
Builder plans to complete the lowering and cleaning of villa foundations this week/beginning of next.
The foundations of the pool will be left in present state due to amount of backfill on site and details of pool still to be finalised. 












4th May 2012
Levels double checked for main villa from initial dig in October. Foundations need to be lowered another 60cm. Decided to leave most of earth on site until after backfill.







3rd May 2012
Big day.....villa brash back on track! 17 months on since that first rainy site visit in early Jan 2011. Plant gear back on site and cleaning the foundations begin.










 




 